It was informed that construction of 157.56 km Miao to Vijoynagar road was delayed due to re-alignment and diversion of the road to avoid the Wildlife sanctuary. It passes through swampy/marshy land thereby incurring huge additional expenses.
However, by putting in the latest technology of road construction (GSB), now the road is constructed successfully along the swampy/marshy land. It was also informed that the road is being divided into package of five parts and around 57% of the total length of the road has been completed so far.
In the meeting, Secretary RWD, Kapa Kholie, Chief Engineer (E/Z), Kago Tabiyo, CE PMGSY, D Nyodu, SE T Tamin, and EE, N Rike were also present.