Arunachal: DC Kra Daadi Pige Ligu inspects road and bridge
Palin
Kra-Daadi District Deputy Commissioner Pige Ligu inspected Yangte-Tali road construction and the bridge construction on river Kumey connecting Tali administrative circle of the district alongwith other HODs of the district on Saturday.
Ligu accompanied by ADC Tali and HODs of Kra Daadi District toured Yangte-Tali Road also to take stock of various developmental activities being taken up under SIDF and Untied Schemes. He also ascertained in the visit took stock of the status of progress.
Tali PWD Division Executive Engineer Bamang Raju informed that the Tower Foundation of both banks and Anchor Blocks of right Bank of Kumey Bridge have been completed. The left Bank Anchor Blocks erection and launching works is going to be completed within 3 months period provided Yangte-Tali Road is open for the movement of heavy vehicles carrying anchor blocks and other bridge’s building materials. The Bridge works are slated to be completed by December 2018.
With regard to construction of road from Kumey Bridge point to Tali ADC Hq, the formation cutting of the road has progressed up to 1.50Km and fair road connectivity to Tali ADC HQ is also slated to be completed by December 2018.
DC while expressing satisfaction on the overall status of the work. He directed the executing agency and the contractor concern to expedite to complete the work before the deadline. He also sought cooperation of the villagers for the smooth and timely completion of this vital works to connect Tali Administrative circle headquarter.